Demolition work began in Arnhem on March 19, 2025 on fire-damaged historic façades in Varkensstraat, with the city saying it wanted to save as much of the old masonry, walls and cellars as possible. The NOS report says the buildings were damaged by the major fire that swept through the city on March 6. What remains standing in some places are only the front façades and sections of stone interior walls.

Officials first looked at whether the walls could be shored up and repaired, but concluded that doing so would take too much time and money without any guarantee of success. That is why the city chose controlled demolition of the unstable parts instead. The decision is important because it shows the line heritage teams often have to walk after a fire: preserving what can be saved while still removing what may collapse.

The process is being carried out step by step and with heritage experts involved at every stage. The contractor said the crew started with the upper parts of the 19th-century façades and then inspected the next structures before deciding what could stay and what had to come down. After talks among the environmental service, structural engineers and heritage specialists, it was later decided that even some lower sections would also have to be demolished.

That careful approach reflects the fact that the area still contains historic material. The city said its ambition was to preserve as much of the historic building walls and cellars as possible, even if unstable sections had to be removed for safety. The source does not say anything about the cause of the March 6 fire, so the article should not venture into that question. Instead, the focus should remain on the post-fire recovery work that is now under way.

Residents and business owners still could not return home or reopen normally while the danger remained and asbestos was being removed from the area. Only after that can utility companies reconnect gas, water and electricity. The demolition is therefore only one part of a longer recovery. In practical terms, Arnhem is still dealing with a fire scene, a preservation problem and a public-safety issue all at once.

The demolition is being managed as a controlled compromise between safety and heritage. Engineers and heritage specialists are trying to save what can still stand, but the report says the lower sections also had to be re-evaluated after the first wave of work. That kind of stepwise demolition is slow, but it reduces the chance that unstable masonry will fall unpredictably and damage what remains.

For the people who live or work nearby, the timing is still dictated by hazards rather than restoration goals. Asbestos removal has to finish before utilities can be restored, and only then can gas, water and electricity be reconnected. The city's preservation ambition is clear, but so is the order of priorities: keep people safe first, stabilize the site second and think about full recovery later.

Because the work is being done in stages, the city is trying to keep as much historic material as possible while eliminating hazards. That balance between preservation and safety is what makes the demolition technically delicate, even if the source gives no timetable beyond saying the work should continue into Friday.